Agapiou, A, Clausen, L E, Flanagan, R, Norman, G and Notman, D (1998) The role of logistics in the materials flow control process: experiences from abroad. Construction Management and Economics, 16(02), 131-7.

Akintoye, A, Bowen, P A and Hardcastle, C (1998) Macro-economic leading indicators of construction contract prices. Construction Management and Economics, 16(02), 159-75.

Alkass, S, Mazerolle, M and Harris, F C (1998) Note - Rigour in research and peer-review: a reply. Construction Management and Economics, 16(02), 139-40.

Burchett, J F and Tummala, V M R (1998) An application of the risk management process (RMP) in capital investment decisions for an EHV transmission line construction project. Construction Management and Economics, 16(02), 235-44.

  • Type: Journal Article
  • Keywords: capital investment; decision analysis; EHV transmission line; risk management
  • ISBN/ISSN: 0144-6193
  • URL: https://doi.org/10.1080/014461998372510
  • Abstract:

    This paper reviews the viability of applying a risk management process to enhance capital investment decisions, when planning the construction of an extra-high voltage (EHV) overhead transmission line project that could be designedand built in the next 10 years by China Light & Power Company Limited, Hong Kong. Different project proposals will be considered for this transmission line as well as different completion dates. Each scenario will be investigated to determine the rate of return and expected cost to customer, using the net present value model. The lowest ’cost to customer’ approach would be the normal criterion for project selection, assuming all proposals are technically viable and compatible with Hong Kong Government infrastructure plans.

Liu, A M-M and Walker, A (1998) Evaluation of project outcomes. Construction Management and Economics, 16(02), 209-19.

Love, P E D, Skitmore, M R and Earl, G (1998) Selecting a suitable procurement method for a building project. Construction Management and Economics, 16(02), 221-33.

Ofori, G (1998) Sustainable construction: comment. Construction Management and Economics, 16(02), 141-5.

Shammas-Toma, M, Seymour, D E and Clark, L (1998) Obstacles to implementing total quality management in the UK construction industry. Construction Management and Economics, 16(02), 177-92.

Wang, C-H and Mei, Y-H (1998) Model for forecasting construction cost indices in Taiwan. Construction Management and Economics, 16(02), 147-57.

Winch, G, Usmani, A and Edkins, A (1998) Towards total project quality: a gap analysis approach. Construction Management and Economics, 16(02), 193-207.